Chapter 10
Questions
1. Determine
the schedule and cost variance for a project that has an actual cost at month 20
of $750,000, a scheduled cost of $600,000 and an earned value of $700,000.
2. Determine
the schedule variance, cost variance, SPI, CPI, and CSI for a project that has
an actual cost at month 12 of $90,000, a scheduled cost of $100,000 and an
earned value of $120,000.
3. A
software development project at day 60 exhibits an actual cost of $300,000 and
a scheduled cost of $375,000. The
software manager estimates a value completed of $300,000. Determine the schedule variance, cost
variance, SPI, CPI, and time variance for the project.
4. A
project to develop a county park has an actual cost in month 24of $240,000, a
planned cost of $290,000, and a value completed of $80,000. Determine the
schedule variance, cost variance, SPI, CPI, and CSI for the project.